Consultancy services for detailed designs and construction supervision of blantyre water supply network upgrades

February 2024

Z&A as the leading firm of a J/V signed a new Water Supply related contract in Malawi. The consulting services include detailed designs and construction supervision of Blantyre Water Supply network upgrades. The Consultancy assignment shall be conducted in two phases: Phase 1–detailed design and tender documentation; and Phase 2–construction supervision and DMA establishment and commissioning.
The assignment shall be completed within a period of Fifty- Eight (58) calendar months.

Phase 1 of the consultancy assignment is expected to be conducted over a period of Ten (10) months and Phase 2 over a period of 48 months ths includes 12 months’ defects liability period)

Below the photo of Overview map of the Blantyre main water assets.

The 3 intakes and Water Treatment Plants are:

  • Walkers Ferry intake on the Shire River and WTP.
  • Mudi Dam intake and WTP
  • Lokhubula River intake and Nguludi WTP