HPP Makrochori II is planned to be constructed on the downstream edge of river Aliakmonas outlet of the existing irrigation canal A0 and is planned to produce electricity when there is no irrigation demand (e.g. in winter months). The existing outlet lies near the village Rapsomaniki. For this project, necessary licenses for production were already obtained. The project was executed in two phases. The first phase included the preparation of preliminary studies for civil and electromechanological works and the second phase (after the Client’s approval) contained the preparation of the detailed design study of the total project. The project was tendered.