Preliminary and detailed design of civil and electromechanological works of the hydroelectric power plant “makrochori ii”, with capacity 4.84 mw

Country: Greece
Client: PPC Renewables S.A.
Year: 2011 - 2012
Funding: National Funds
Contract Value: 94,050.00 € (129,456 US$)

Preliminary and detailed design of civil and electromechanological works of the hydroelectric power plant “makrochori ii”, with capacity 4.84 mw

Country: Greece
Client: PPC Renewables S.A.
Year: 2011 - 2012
Funding: National Funds
Contract Value: 94,050.00 € (129,456 US$)

HPP Makrochori II is planned to be constructed on the downstream edge of river Aliakmonas outlet of the existing irrigation canal A0 and is planned to produce electricity when there is no irrigation demand (e.g. in winter months). The existing outlet lies near the village Rapsomaniki. For this project, necessary licenses for production were already obtained. The project was executed in two phases. The first phase included the preparation of preliminary studies for civil and electromechanological works and the second phase (after the Client’s approval) contained the preparation of the detailed design study of the total project. The project was tendered.

Technical evaluation of the small hydroelectric power plant “argiri” with capacity of 6,35 mw in argithea municipality, central greece

Country: Greece
Client: PROTERGIA S.A.
Year: 2011 - 2012
Funding: Private Investment Fund
Contract Value: 19,680.00€ (26,684 US$)

Technical evaluation of the small hydroelectric power plant “argiri” with capacity of 6,35 mw in argithea municipality, central greece

Country: Greece
Client: PROTERGIA S.A.
Year: 2011 - 2012
Funding: Private Investment Fund
Contract Value: 19,680.00€ (26,684 US$)

The project involved the technical evaluation of the design and operation of the small hydropower plant “Argyri”. The evaluation included a review of the hydrology of the basin, the review of the geological and geotechnical parameters of the project, the review of the hydraulic design of the intake facilities and the evaluation of the installed electro-mechanical equipment, including gates, control boards, the turbine and generator complex and the associated facilities. It was found that the plant was generally well designed and built, apart from several intake design inefficiencies which caused unnecessary delays and stop-downs, especially during times of crucial peak load operations. The study resulted in a number of proposals to improve the plant operation, mainly through structural improvements of the intake works.

Design of the new railway line connection between the existing network and the commercial port of kavala city, east macedonia, greece

Country: Greece
Client: ERGOSE S.A.
Year: 2011 - 2013
Funding: Inter-European Transport Networks
Contract Value: 2,364,846.00€

Design of the new railway line connection between the existing network and the commercial port of kavala city, east macedonia, greece

Country: Greece
Client: ERGOSE S.A.
Year: 2011 - 2013
Funding: Inter-European Transport Networks
Contract Value: 2,364,846.00€

The scope of the project consisted of the preliminary and detailed design of the water drainage system of the new single railway line connecting the commercial port of Kavala city to the existing railway line from Thessaloniki to Alexandroupoli, near the Toxotes area in Xanthi prefecture. Furthermore it included the service road drainage system along with the flood protection system from surrounding catchment areas with the necessary hydraulic structures (ditches, culverts, etc). The contract also involved the restoration of the existing irrigation networks. The project was divided into two parts. The first part involved the preliminary design of the water drainage system of the new single railway line(14,4Km).The second part involved the drainage system of the new single railway line(17.4Km).The new single railway line was designed parallel nearby the existing highway Egnatia so that most of the constructed culverts were designed to be extended to the railway line and be checked for design capacity.Three railway bridges were designed in preliminary stage over the Asprohomatos stream, the Xiropotamos stream and Nestos River that were checked for the design flow of T=100 yrs.

Water management project of river basins in the water districts of east macedonia and thrace according to specifications of the e.u. Directive 2000 /60/ec

Country: Greece
Client: East Macedonia and Thrace Perfectures
Year: 2011 - 2013
Funding: 80% EU Funds, 20% National Funds
Contract Value: 1,530,301.00 € (2,042,033.00 USD)

Water management project of river basins in the water districts of east macedonia and thrace according to specifications of the e.u. Directive 2000 /60/ec

Country: Greece
Client: East Macedonia and Thrace Perfectures
Year: 2011 - 2013
Funding: 80% EU Funds, 20% National Funds
Contract Value: 1,530,301.00 € (2,042,033.00 USD)

The project concerned two out of the total fourteen River Basin Districts (RBDs) of Greece, Eastern Macedoniaand Thrace. The project is about the provision of services to complete and extend the outcomes of previous national actions leading up to the implementation of the EU Water Framework Directive (2000/60/EC) in these two RBDs and to the publication of the first River Basin District Management Plans. In detail the following actions took place:1) Modification, completion and bringing up to date previous actions, 2) Preparation of the necessary reports and GIS files and databases, 3)Preparation of a Strategic EIA for the actions and measures proposed in the RBD Management Plan, 4) Preparation of an emergency drought contingency plan, 5) Organizing and participating in the public consultation process with the RBD’s stakeholders 6) Completion of the client’s database systems with the updated information 7) Preparation of the necessary files for reporting the results to the European Commission (WISE) 8) Publishing the River Basin District Management Plans on internet and creating the awareness to the public, 9) Publishing documentations on climate change and other environmental issues 10) Organizing international workshops, training courses, internet site, documentation and manuals.

Preliminary and detailed design for the allignment and regulation of kanapitsa stream from sta. 0+000 (outfall to river kifisos) to sta. 12+000

Country: Greece
Client: Ministry of Economy, Infrastructure, Shipping and Tourism
Year: 2010 - 2015
Funding: National Funds
Contract Value: 724,371.00€

Preliminary and detailed design for the allignment and regulation of kanapitsa stream from sta. 0+000 (outfall to river kifisos) to sta. 12+000

Country: Greece
Client: Ministry of Economy, Infrastructure, Shipping and Tourism
Year: 2010 - 2015
Funding: National Funds
Contract Value: 724,371.00€

The Acharnon (Kanapitsa) stream collects the runoff from the southern part of Parnitha mountain, the western part of the Thrakomakedones region and the eastern part of Menidi district (total area of the basin: 16,3 Km²). It flows from north to south and outflows into the main river of Kifisos immediately south of the Kokkinos Mylos Cemetery. The study concerns the design of Kanapitsa stream relining works that will allow the stream to serve as the main floodwater collector of the area, enabling its effective stormwater drainageThe performed activities included all required surveys (topographical, geotechnical, geological, socioeconomic etc), the preparation of preliminary and detailed design of all the required works and the preparation of the Environmental and socio impact study.

Hydrogeological study for the artificial enrichment of the carstic limestone system of titarisios and pineios rivers, tyrnavos area, larisa

Country: Greece
Client: Region Unit of Larisa
Year: 2010 - 2012
Funding: National Funds
Contract Value: 230,138.00 € (319,891 .00 USD)

Hydrogeological study for the artificial enrichment of the carstic limestone system of titarisios and pineios rivers, tyrnavos area, larisa

Country: Greece
Client: Region Unit of Larisa
Year: 2010 - 2012
Funding: National Funds
Contract Value: 230,138.00 € (319,891 .00 USD)

The scope of this study was the recording of the technical data, the necessary tasks and the required field work to understand the behavior of the carstic system on Titarisios and Pineios Rivers, and the development of a mathematical model for the system. The overall study area included the semi-crystallic limestones in Damasi and Tyrnavos areas and on river Titarisios region, together with the Elassona and Potamia basins, and the river Pineios. The total area of the study was 300 km². This hydrogeological study aimed at: 1) To estimate the quantitative and qualitative water balance of the region under study,2) To inform the sustainable use of surface water and groundwater for irrigation of agricultural land, water supply to settlements and other uses 3) To calculate the available quantities from aquifers throughout the year, without causing adverse impacts on them, 4) To formulate the relationship of surface – groundwater and the most environmental way of exploitation 5) To formulate specific proposals for the enrichment of groundwater aquifers from surface waters.

Installation of a monitoring system & evaluation of the environmental status of rivers louros & arachthos and the amvrakikos golf, west greece

Country: Greece
Client: Arta Prefecture Authority
Year: 2009 - 2010
Funding: National Funds
Contract Value: 909,983.19 € (1,338,210.00 USD)

Installation of a monitoring system & evaluation of the environmental status of rivers louros & arachthos and the amvrakikos golf, west greece

Country: Greece
Client: Arta Prefecture Authority
Year: 2009 - 2010
Funding: National Funds
Contract Value: 909,983.19 € (1,338,210.00 USD)

The main objective of the assignment was to inerprete and combine aerial photography coverage of the area of the catchments basins of Louros and Arachthos rivers which drain into Amvrakikos Gulf (dating back to 1945) and current high resolution satellite imagery to create a number of thematic maps showing the changes effected over time by urban and agricultural development. Changes over time were mapped for river courses, river beds, wetland areas and riparian areas along the Louros and Arachthos rivers and for the lagoons formed on the northern shores of Amvrakikos Gulf. Historical aerial photographs were scanned and assembled into a seamless mosaic, georeferenced to the current Greek projection system and datum. From this background, important elements of the river environment were digitized (banks, riparian areas, flood plains, etc.) and stored into a GIS system. The same elements were digitized from current high resolution satellite imagery of the area and the two data sets were compared using the GIS. Important metrics such as differences in floodplain areas, riparian extent, lagoon coverage etc. were calculated from superposition of the two different datasets thus quantifying the physical changes in the river environment over time.

Detailed design for rehabilitation of irrigation & water supply networks in deskati, chasia and eani municipalities, west macedonia, north greece

Country: Greece
Client: Public Power Corporation (PPC S.A.)
Year: 2009 - 2011
Funding: Public Power Corporation (PPC S.A.)
Contract Value: 234,000.00 € (334,285.00 USD)

Detailed design for rehabilitation of irrigation & water supply networks in deskati, chasia and eani municipalities, west macedonia, north greece

Country: Greece
Client: Public Power Corporation (PPC S.A.)
Year: 2009 - 2011
Funding: Public Power Corporation (PPC S.A.)
Contract Value: 234,000.00 € (334,285.00 USD)

This study was about the rehabilitation of the existing irrigation network system, the affected water supply networks in villages Paliouria, Katakali, Dimitra and Chromio and the reformation of the irrigation networks. The study was separated in two phases following the construction phases proposed by the client. The design included: Phase A: An irrigable area of 560ha was covered. The components of the system were :a) A system of two pumping stations at the lake and nearby the lake respectively b) A new 6300 m long gravity pipe supplying with water zone E2 from the new tank and the rehabilitation and reformation of the existing network of 250ha. c) Two completely new irrigation networks covering and area of 310 ha d) A new water supply network for the village of Paliouria, consisting of a new pumping station, a new water tank and a 5.800 m pipe . e) A new water supply network for an area near the village Chromio. Phase B consisted of the Detailed Design and the preparation of the Tender Documents of the above irrigation and water supply systems

Water resources assessment study on smixiotikos river basin, grevena prefecture, west macedonia, north greece

Country: Greece
Client: West Macedonia Regional Authority
Year: 2009 - 2009
Funding: Regional Funds
Contract Value: 12,000.00 € (15,649.00 USD)

Water resources assessment study on smixiotikos river basin, grevena prefecture, west macedonia, north greece

Country: Greece
Client: West Macedonia Regional Authority
Year: 2009 - 2009
Funding: Regional Funds
Contract Value: 12,000.00 € (15,649.00 USD)

The Water Resources Assessment Study of the river Smixiotikos included the following: 1) Collection of all the relevant environmental, hydrological and hydro geological information,2) Development of an integrated database and presentation of all the relevant data on maps (GIS),3) Recording of all activities related to water use and estimation of water demand for each category of use 4) Use of simulation software (MIKE BASIN & MIKE SHE) 5) Analysis of developing projects in the greater area and determination of current and future water needs 6) Dissemination actions: workshops, training courses, internet site development, documentation and manuals.

Final design of connection road between preveza town and the e-65 motorway, preveza prefecture, hpeiros district, west greece

Country: Greece
Client: Ministry of Public Works
Year: 2009 - In progress
Funding: European Cohesion Fund
Contract Value: 3,734,034.28€

Final design of connection road between preveza town and the e-65 motorway, preveza prefecture, hpeiros district, west greece

Country: Greece
Client: Ministry of Public Works
Year: 2009 - In progress
Funding: European Cohesion Fund
Contract Value: 3,734,034.28€

The study involves the road water drainage system 33Km long , the flood protection system from the surrounding catchment areas with all the necessary hydraulic structures (ditches, culverts, etc).It also involves the evaluation of the hydrology data of the area and the production of new flow curves for the main streams and rivers crossing the road, with main river Louros included (a new high bridge has been designed for this area).